HUD Mortgagee Letter 2023-02 — Expansion of the COVID-19 Recovery Loss Mitigation Options

hud-ml-2023-02

HUD ML 2023-02 expands the COVID-19 Recovery Loss Mitigation Options to include all Borrowers in Default or Imminent Default (including Non-Occupant Borrowers), increases the COVID-19 Recovery Partial Claim to 30 percent of UPB, temporarily suspends FHA-HAMP and Standard PFS/DIL options through October 30, 2024, and updates SFDMS reporting.

Get this register: .xlsx .csv More bundles →

Verbatim regulatory text (3)

Verbatim provisions from HUD Mortgagee Letter 2023-02 — Expansion of the COVID-19 Recovery Loss Mitigation Options — each quote is a verified substring of the regulator-published source snapshot, not retyped. Quoted for reference; this is not legal advice. The operational layer (P&P updates, prompts) lives in the regulation update kits.

HUD ML 2023-02 — Effective Date

The provisions of this ML may be implemented immediately, but must be implemented no later than April 30, 2023, where the Mortgagee has not sent documents to the Borrower to complete any Home Retention Option.

Source: HUD ML 2023-02 — Effective Date · source URL · snapshot 3ee9efb92171f8b9

HUD ML 2023-02 — COVID-19 Recovery Option End Dates

The COVID-19 Recovery Options may be offered through, but no later than, October 30, 2024, and completed no later than February 27, 2025.

Source: HUD ML 2023-02 — Effective Date / Sunset Dates · source URL · snapshot 3ee9efb92171f8b9

HUD ML 2023-02 — FHA-HAMP Temporarily Suspended (III.A.2.k.v(B))

All FHA-HAMP Options are temporarily suspended and must not be offered through October 30, 2024. Mortgagees must evaluate all Borrowers for the COVID-19 Recovery Home Retention Options.

Source: HUD ML 2023-02 — III.A.2.k.v(B) · source URL · snapshot 3ee9efb92171f8b9